Re: Indoor facility

Post by AFCAT » Sat Jul 01, 2023 10:04 pm

I thought I read when they broke ground that the facility was suppose to be completed in September 2023, but I found this article from December that indicates the facility will be completed by the end of 2023.

https://www.bozemandailychronicle.com/n ... 4fe2c.html


QB Club https://www.msubqc.org
Bobcat Collective https://bobcatcollective.com/

Bobcat athletics is a business to the coaches, school leadership, and players. It's time the fans treat Bobcat athletics as a business too.

4KornerKat
BobcatNation Team Captain
Posts: 453
Joined: Thu Oct 06, 2016 5:38 pm

Re: Indoor facility

Post by 4KornerKat » Sun Jul 02, 2023 7:02 am

I think it may have actually bumped back again to May of 2024. 24 months probably wasn't realistic for that magnitude of project.



User avatar
catatac
Golden Bobcat
Posts: 9677
Joined: Mon Mar 29, 2004 1:37 pm

Re: Indoor facility

Post by catatac » Sun Jul 02, 2023 11:41 am

4KornerKat wrote:
Sun Jul 02, 2023 7:02 am
I think it may have actually bumped back again to May of 2024. 24 months probably wasn't realistic for that magnitude of project.
Where are you seeing this?


Great time to be a BOBCAT!

Andy
BobcatNation Redshirt
Posts: 43
Joined: Mon Mar 30, 2015 2:34 pm

Re: Indoor facility

Post by Andy » Sun Jul 02, 2023 2:25 pm

Construction of Grizzly Indoor Practice Facility stalls, affecting November target date
Bill Speltz Jun 20, 2023 Updated Jun 24, 2023



Andy
BobcatNation Redshirt
Posts: 43
Joined: Mon Mar 30, 2015 2:34 pm

Re: Indoor facility

Post by Andy » Sun Jul 02, 2023 2:27 pm

Sorry read the thread wrong.



TomCat88
Golden Bobcat
Posts: 20900
Joined: Thu Oct 23, 2008 6:16 am
Location: An endless run of moguls

Re: Indoor facility

Post by TomCat88 » Sun Jul 02, 2023 5:21 pm

Andy wrote:
Sun Jul 02, 2023 2:27 pm
Sorry read the thread wrong.
Uh-huh, yeah, sure ya did. :wink:


MSU - 16 team National Champions (most recent 2024); 57 individual National Champions (most recent 2023).
toM StUber

User avatar
allcat
Golden Bobcat
Posts: 8879
Joined: Mon Nov 02, 2009 5:13 pm
Location: 90 miles from Nirvana (Bobcat Stadium)

Re: Indoor facility

Post by allcat » Sun Jul 02, 2023 5:33 pm

Andy wrote:
Sun Jul 02, 2023 2:25 pm
Construction of Grizzly Indoor Practice Facility stalls, affecting November target date
Bill Speltz Jun 20, 2023 Updated Jun 24, 2023
I can't believe you would post that name, in it's evil form, in the sanctified annals of the BOBCAT football forum. At least edit for the correct version of gris.


Geezer. Part Bionic,. Part Iconic

4KornerKat
BobcatNation Team Captain
Posts: 453
Joined: Thu Oct 06, 2016 5:38 pm

Re: Indoor facility

Post by 4KornerKat » Sun Jul 02, 2023 5:40 pm

catatac wrote:
Sun Jul 02, 2023 11:41 am
4KornerKat wrote:
Sun Jul 02, 2023 7:02 am
I think it may have actually bumped back again to May of 2024. 24 months probably wasn't realistic for that magnitude of project.
Where are you seeing this?
I heard it through the grapevine?



User avatar
vike_king
BobcatNation Hall of Famer
Posts: 3259
Joined: Fri Oct 07, 2005 12:51 pm
Location: Helena, MT/Chester, MT/Fort Benton, MT

Re: Indoor facility

Post by vike_king » Mon Jul 03, 2023 11:35 pm

Common Cat wrote:
Sat Jul 01, 2023 6:11 pm
TomCat88 wrote:
Sat Jul 01, 2023 5:29 pm
Looks huge. Oh to be young again.
That’s what she….
Dang it, too late again!!


Chester, MT/ Helena, MT

TomCat88
Golden Bobcat
Posts: 20900
Joined: Thu Oct 23, 2008 6:16 am
Location: An endless run of moguls

Re: Indoor facility

Post by TomCat88 » Tue Jul 04, 2023 7:50 am

vike_king wrote:
Mon Jul 03, 2023 11:35 pm
Common Cat wrote:
Sat Jul 01, 2023 6:11 pm
TomCat88 wrote:
Sat Jul 01, 2023 5:29 pm
Looks huge. Oh to be young again.
That’s what she….
Dang it, too late again!!
A poorly thought out post on my part. :oops:


MSU - 16 team National Champions (most recent 2024); 57 individual National Champions (most recent 2023).
toM StUber

User avatar
AFCAT
Golden Bobcat
Posts: 12979
Joined: Mon Sep 12, 2016 3:25 pm

Re: Indoor facility

Post by AFCAT » Sun Sep 17, 2023 5:46 pm

Took a few photos on Saturday of the fitness center progress. They still have a long way to go.

Image

Image

Image

Image

Image


QB Club https://www.msubqc.org
Bobcat Collective https://bobcatcollective.com/

Bobcat athletics is a business to the coaches, school leadership, and players. It's time the fans treat Bobcat athletics as a business too.

User avatar
RICO CAT
Honorable Mention All-BobcatNation
Posts: 760
Joined: Fri Apr 16, 2021 2:36 pm

Re: Indoor facility

Post by RICO CAT » Sun Sep 17, 2023 6:38 pm

Wow, that looks great, really like all the windows. Thanks for the update AFCAT.


“OVER THEM MOUNTAINS”

User avatar
RickRund
Golden Bobcat
Posts: 8064
Joined: Tue Jun 22, 2010 6:08 pm
Location: Post Falls ID

Re: Indoor facility

Post by RickRund » Mon Sep 18, 2023 1:35 pm

Any timeline?


msubobcats@outlook.com
Audiatur et altura pars: Let both sides be fairly heard.
Audi alteram partem: listen to the other side.

TomCat88
Golden Bobcat
Posts: 20900
Joined: Thu Oct 23, 2008 6:16 am
Location: An endless run of moguls

Re: Indoor facility

Post by TomCat88 » Mon Sep 18, 2023 2:02 pm

SDSU has a nice fitness center on campus that is open to public. I used it for $10. Is MSU going to allow it to be used by the public?


MSU - 16 team National Champions (most recent 2024); 57 individual National Champions (most recent 2023).
toM StUber

User avatar
snarf
BobcatNation Letterman
Posts: 147
Joined: Fri Nov 09, 2012 9:17 am

Re: Indoor facility

Post by snarf » Mon Sep 18, 2023 2:14 pm

TomCat88 wrote:
Mon Sep 18, 2023 2:02 pm
SDSU has a nice fitness center on campus that is open to public. I used it for $10. Is MSU going to allow it to be used by the public?
General public, no, unless they are there with a member. Alumni yes. https://www.montana.edu/campusrec/membe ... bpage.html

Interestingly, there is a specific Montana law that covers this so university fitness centers are not in competition with local, private businesses.
https://leg.mt.gov/bills/2001/billhtml/SB0151.htm



CATCO
BobcatNation Letterman
Posts: 199
Joined: Fri Apr 02, 2004 2:35 pm
Location: Bozeman

Re: Indoor facility

Post by CATCO » Mon Sep 18, 2023 2:41 pm

RFQ out for the indoor facility, $15M budget with a spring start date and winter 2024/25 completion.

The Indoor Practice Facility project at Montana State University in Bozeman, MT is a new “ground up" athletic facility located immediately southwest of the existing Bobcat Stadium, and north of existing irrigation pond facility. The site is on an existing parking lot and landscaping yard. The primary structure will be a pre-engineered, metal framed, tensioned fabric exterior building, which houses a 100 yard (two 10 YD endzones with 80 YD striped field between) artificial turf football field. Attached to the metal building will be a stick-built support building that will include entry lobby, restrooms, changing areas, storage, and mechanical space. The project also includes site improvements to the immediate surrounding site, including the landscape area around the building and a small parking area for the required ADA parking. A fire lane may need to be required along the south elevation. The rest of the parking will be part of another project adjacent to the main stadium, not in this scope but will have to be coordinated with other engineering firms.



msutrackfan
BobcatNation Letterman
Posts: 158
Joined: Sat Mar 10, 2007 8:45 pm

Re: Indoor facility

Post by msutrackfan » Fri Sep 22, 2023 12:09 pm

CATCO wrote:
Mon Sep 18, 2023 2:41 pm
RFQ out for the indoor facility, $15M budget with a spring start date and winter 2024/25 completion.

The Indoor Practice Facility project at Montana State University in Bozeman, MT is a new “ground up" athletic facility located immediately southwest of the existing Bobcat Stadium, and north of existing irrigation pond facility. The site is on an existing parking lot and landscaping yard. The primary structure will be a pre-engineered, metal framed, tensioned fabric exterior building, which houses a 100 yard (two 10 YD endzones with 80 YD striped field between) artificial turf football field. Attached to the metal building will be a stick-built support building that will include entry lobby, restrooms, changing areas, storage, and mechanical space. The project also includes site improvements to the immediate surrounding site, including the landscape area around the building and a small parking area for the required ADA parking. A fire lane may need to be required along the south elevation. The rest of the parking will be part of another project adjacent to the main stadium, not in this scope but will have to be coordinated with other engineering firms.
From this description, there are no plans to put a track around the outside to accommodate the T&F program. Curious to know if there was ever an additional cost estimate to include the track and it was then decided that the final cost would be more than could be afforded.



User avatar
AFCAT
Golden Bobcat
Posts: 12979
Joined: Mon Sep 12, 2016 3:25 pm

Re: Indoor facility

Post by AFCAT » Fri Sep 22, 2023 12:32 pm

msutrackfan wrote:
Fri Sep 22, 2023 12:09 pm
CATCO wrote:
Mon Sep 18, 2023 2:41 pm
RFQ out for the indoor facility, $15M budget with a spring start date and winter 2024/25 completion.

The Indoor Practice Facility project at Montana State University in Bozeman, MT is a new “ground up" athletic facility located immediately southwest of the existing Bobcat Stadium, and north of existing irrigation pond facility. The site is on an existing parking lot and landscaping yard. The primary structure will be a pre-engineered, metal framed, tensioned fabric exterior building, which houses a 100 yard (two 10 YD endzones with 80 YD striped field between) artificial turf football field. Attached to the metal building will be a stick-built support building that will include entry lobby, restrooms, changing areas, storage, and mechanical space. The project also includes site improvements to the immediate surrounding site, including the landscape area around the building and a small parking area for the required ADA parking. A fire lane may need to be required along the south elevation. The rest of the parking will be part of another project adjacent to the main stadium, not in this scope but will have to be coordinated with other engineering firms.
From this description, there are no plans to put a track around the outside to accommodate the T&F program. Curious to know if there was ever an additional cost estimate to include the track and it was then decided that the final cost would be more than could be afforded.
I’m sure there was an estimate and that might be part of the reason this project has been delayed. I know I’d love to see track have a true indoor facility like the one envisioned in the master plan.


QB Club https://www.msubqc.org
Bobcat Collective https://bobcatcollective.com/

Bobcat athletics is a business to the coaches, school leadership, and players. It's time the fans treat Bobcat athletics as a business too.

User avatar
kmax
Site Admin
Posts: 9783
Joined: Sat Mar 06, 2004 6:23 pm
Location: Belgrade, MT
Contact:

Re: Indoor facility

Post by kmax » Fri Sep 22, 2023 1:47 pm

AFCAT wrote:
Fri Sep 22, 2023 12:32 pm
msutrackfan wrote:
Fri Sep 22, 2023 12:09 pm
CATCO wrote:
Mon Sep 18, 2023 2:41 pm
RFQ out for the indoor facility, $15M budget with a spring start date and winter 2024/25 completion.

The Indoor Practice Facility project at Montana State University in Bozeman, MT is a new “ground up" athletic facility located immediately southwest of the existing Bobcat Stadium, and north of existing irrigation pond facility. The site is on an existing parking lot and landscaping yard. The primary structure will be a pre-engineered, metal framed, tensioned fabric exterior building, which houses a 100 yard (two 10 YD endzones with 80 YD striped field between) artificial turf football field. Attached to the metal building will be a stick-built support building that will include entry lobby, restrooms, changing areas, storage, and mechanical space. The project also includes site improvements to the immediate surrounding site, including the landscape area around the building and a small parking area for the required ADA parking. A fire lane may need to be required along the south elevation. The rest of the parking will be part of another project adjacent to the main stadium, not in this scope but will have to be coordinated with other engineering firms.
From this description, there are no plans to put a track around the outside to accommodate the T&F program. Curious to know if there was ever an additional cost estimate to include the track and it was then decided that the final cost would be more than could be afforded.
I’m sure there was an estimate and that might be part of the reason this project has been delayed. I know I’d love to see track have a true indoor facility like the one envisioned in the master plan.
We were told that it was considered but the costs of something like was in the original master plan was just way too much with the increases in building costs since that plan was put out. Waiting to fund that type of facility would have meant years to decades before getting an indoor facility most likely.


“Arguing with anonymous strangers on the Internet is a sucker's game because they almost always turn out to be—or to be indistinguishable from—self-righteous sixteen-year-olds possessing infinite amounts of free time.” -- Neal Stephenson, Cryptonomicon

User avatar
DMMDCats
2nd Team All-BobcatNation
Posts: 1230
Joined: Sat Aug 25, 2018 5:21 pm
Location: in a very unimportant part of the galaxy
Contact:

Re: Indoor facility

Post by DMMDCats » Fri Sep 22, 2023 7:52 pm

Calling Nick…
Calling Sir Nick…

Bring your Dubai buddy and donate a bldg or 3.